8.5.6 Installing Genset Control Signal Cables

NO TICE
For a genset that starts when the dry contact is open, connect the signal cable to
ports NO and COM. For a genset that starts when the dry contact is closed,
connect the signal cable to ports NC and COM.
Procedure
Step 1 Install genset control signal cables.