Before installing front or rear components into the chassis, review chassis bay numbering for each
component. For slot numbering information, see the quick setup instructions.
Based on the total number ordered and the planned configuration, install the following components:
Nodes
Power supplies
System fans
For more information, see the appropriate chassis setup and installation guide and the node installation
instructions.

Installing the server into the chassis

WARNING: This server is very heavy. To reduce the risk of personal injury or damage to the
equipment:
• Observe local occupational health and safety requirements and guidelines for manual
material handling.
• Get help to lift and stabilize the product during installation or removal, especially when the
product is not fastened to the rails. Hewlett Packard Enterprise recommends that a
minimum of two people are required for all rack server installations. A third person may be
required to help align the server if the server is installed higher than chest level.
• Use caution when installing the server in or removing the server from the rack; it is unstable
when not fastened to the rails.
Insert the system tray into the chassis.
1.
Rotate the tray handle to lock.
2.
Connect peripheral devices to the server.
3.
WARNING: To reduce the risk of electric shock, fire, or damage to the equipment, do not plug
telephone or telecommunications connectors into RJ-45 connectors.
Connect the power cords to the power supplies.
4.
Connect the power cord to the AC power source.