Section 7
Electrical System and Components
Test 2. Solenoid Pull-In Coil/Contact Continuity Test.
connect the two ohmmeter leads to the two large post
indicate continuity, if no continuity is indicated the
12 volt Test Leads
Momentary
Connection Only
Figure 7-69. Testing Pull-In Coil/Solenoid Contact
Continuity.
Test 3. Solenoid Hold-In Coil Function Test.
terminal on the solenoid, and the other lead to the
Manually Push
Plunger "In"
12 volt Test Leads
Connect Only Long
Enough to Test
Figure 7-70. Testing Hold-In Coil/Function Test.
7.36
Test 4. Solenoid Hold-In Coil/Contact Continuity Test.
connect the two ohmmeter leads to the two large post
continuity, if no continuity is indicated the solenoid
condition.
VOM Leads
Figure 7-71. Testing Hold-In Coil/Solenoid Contact
Continuity.
VOM Meter
Leads
Plunger
Pushed "In"
12 volt Test Leads