Mechanical Installation; Civil Works; Using Wallbox Installation-Kit - Wallbox Supernova Installation Manual

Hide thumbs Also See for Supernova:
Table of Contents

Advertisement

PRODUCT DESCRIPTION AND SITE PREPARATION
Door and Keys Instructions
5.
To open the right side door, press the
buttons placed inside of Supernova.
To close the charger, start from the right doors. Then, close the front
door and finally lock the door on the left side by using the key.
REMEMBER
When closing the door, apply equal pressure on the upper, middle
and bottom to ensure that the buttons close correctly.
26

MECHANICAL INSTALLATION

Civil Works

Using Wallbox installation-kit

Structural engineering work must be carried out in accordance
with current regulations and as specified below:
• The concrete used for the foundation must be a standard
ready-mix concrete and be resistant to frost.
• The charger must be fixed to the ground and be perfectly level. In fact, if
the charging point leaves a gap from the ground (by lifting the right, left,
front or rear), it could damage the permeability of the Supernova.
• It will be necessary to level the system without the use of washers or
other objects that do not guarantee integral and continuous contact
between the base of the charging point and the ground.
• To ensure the optimal installation and the durability of the Supernova,
use the foundation kit (template and concrete base).
• To perform the electrical connection, make sure not to cut the tube at the sole
level to avoid the water penetrating into the charger in case of rain.
Steps
Material
Assembly
Part
Size
Foundation
Level Plate
360x701 mm
Supernova
Foundation
DIN 976-1 B
M16 x 500 mm
Foundation
NUT DIN 934
M16
Quantity
Tools recommended
2
Not Applicable
4
Not Applicable
16
2x Spanner (size 24 mm)
27