Prefabricated Concrete Foot With Wallbox Compatible Mounting Plate; Chemical Anchors In Concrete - Wallbox Supernova Installation Manual

Hide thumbs Also See for Supernova:
Table of Contents

Advertisement

MECHANICAL INSTALLATION
Civil Works
30
5.
Fill the concrete base to ground level.
The lower plate should be buried in the
concrete, 0.45 m below ground. On the
upper plate, the four threaded rods should
protrude 0.04 to 0.06 m from the ground.
REMEMBER
The concrete shall never exceed the
upper level plate to ensure that Supernova
anchors on a flat surface.
6.
Let the concrete dry completely. It is
recommended that the cables stick at
least 1m out from the surface in order to
proceed with the electrical connection of
Supernova.
REMEMBER
Concrete dries at different rates depending
on humidity, temperature and on the
provider. It is important to make sure it is
completely dry before proceeding with the
next steps.
MECHANICAL INSTALLATION
Civil Works
The civil works can be carried out using the following procedures:
• Prefabricated concrete foot
• Chemical anchors
• Wallbox mounting kit

Prefabricated concrete foot with Wallbox compatible mounting plate

Check the manual provided by the supplier of the prefabricated
concrete foot, before proceeding with the installation.

Chemical anchors in concrete

1. Using the level plate as an indicator, drill to make 4 holes in
the concrete substrate and remove the crumbs and debris
from the floor. Each hole should be 0,45 m depth.
2. Brush the holes to smooth the surface and
remove the debris from the holes.
3. Use a caulk gun to fill the holes with the epoxy.
4. Take the 4 chemical anchor bolts M16 and place each one of them in
one hole, making sure to rotate them while pushing them to the bottom
of the holes. They should protrude around 0.05 m from the ground.
IMPORTANT
Make sure the drilling is bigger than M16 to ensure
the entrance of the bolts after the epoxy.
5. Clean the excess of the product with some cardboard to spread it around.
6. Let the product dry completely.
7. At this point, place the upper plate and place the charger using a forklift
or a crane in correspondence with the bars. The four holes present at the
base of Supernova need to be aligned with the bars coming out of the floor.
8. Fix the chargers with 4 M16 washers and 4 M16 screws.
IMPORTANT
Make sure the drilling is bigger than M16 to ensure
the entrance of the bolts after the epoxy.
31

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents