Figure 4-37 Installing battery communications cables
(1) Full-capacity cabinet (7+7 scenario)
Step 5 Install battery copper bars and power cables.
1.
2.
3.
● When installing a copper bar, connect the part with a round hole to the upper
● Excessive bolts will be used as spare parts.
After removing the safety cap from the power cable of the battery at the bottom
layer, install the cable immediately to prevent the exposed terminal from touching
the shell, which may cause sparks or burns.
Issue 09 (2022-01-30)
Open the terminal protective covers, install copper bars between battery
modules, and close the terminal protective covers.
Open the terminal protective covers, install copper bars between battery
modules and fuses, and close the terminal protective covers.
Open the terminal protective covers, install the battery power cables reserved
in the cabinet, and close the terminal protective covers.
NO TICE
battery module, and connect the part with a slotted hole to the lower battery
module. Install the part with a round hole first, and then the part with a slotted
hole.