Huawei iBAT 2.0-CIM01C2 Quick Manual
Huawei iBAT 2.0-CIM01C2 Quick Manual

Huawei iBAT 2.0-CIM01C2 Quick Manual

Hide thumbs Also See for iBAT 2.0-CIM01C2:

Advertisement

Quick Links

iBAT 2.0-CIM01C2
Quick Guide
Issue: 06
BOM Number: 31010VJT
Date: 2020-03-20
1
Product Introduction
Name
Model
CIM
CIM01C2
BIM
BIM01C3
BIM02C1
1. The information in this document is subject to change without notice. Every effort has been made
in the preparation of this document to ensure accuracy of the contents, but all statements,
information, and recommendations in this document do not constitute a warranty of any kind,
express or implied.
2. This document describes the procedure for installing the CIM and BIM. Read the iBAT 2.0-
CIM01C2 User Manual before installation to learn the product information and safety precautions.
3. Use insulated tools when installing the equipment.
4. Only Huawei engineers or engineers certified by Huawei are allowed to install and maintain the
CIM and BIM. Otherwise, personal injury or equipment damage may occur, and the resulting
equipment faults are beyond the warranty scope of Huawei.
2
Installing Equipment (Battery Cabinet)
2.1
Installation Position
BIM installation position
BIM
Function
Intelligent battery
management module
12 V intelligent battery
monitoring module
2 V intelligent battery
monitoring module
Battery
Hall effect sensor
Copyright © Huawei Technologies Co., Ltd. 2020. All rights reserved.
Description
One CIM can support a maximum of 300
BIMs, and manage BIMs of a maximum of
four battery strings.
The two models of BIMs are installed and
commissioned in the same manner. This
document uses the BIM01C3 as an example.
CIM installation position
CIM
1
BIB
Battery
cabinet

Advertisement

Table of Contents
loading

Summary of Contents for Huawei iBAT 2.0-CIM01C2

  • Page 1 CIM01C2 User Manual before installation to learn the product information and safety precautions. 3. Use insulated tools when installing the equipment. 4. Only Huawei engineers or engineers certified by Huawei are allowed to install and maintain the CIM and BIM. Otherwise, personal injury or equipment damage may occur, and the resulting equipment faults are beyond the warranty scope of Huawei.
  • Page 2 • The battery appearance is for reference only. • In the figure, the circuit breaker panel of the battery cabinet has been removed. Before removing the circuit breaker panel, knock off the cover on the CIM indicator hole on the panel. •...
  • Page 3 3. After connecting all power cables to the system, connect the BIM cable to the BIM panel port. • Before connecting the cable to the BIM panel port, connect all power cables to the system. • Before disconnecting the BIM cable, disconnect the cable from the BIM panel port.
  • Page 4: Installation Position

    Installing Equipment (Battery Rack) Installation Position BIM installation position Top installation Side installation Battery Battery The battery appearance is for reference only. CIM installation position Top installation Side installation BCB box BCB box Hall effect Hall effect sensor sensor...
  • Page 5 • When selecting a position to install the CIM, ensure that the communication distance between the CIM and the BIM is not greater than 15 meters. • Dimensions (L x W) of the center hole of the Hall effect sensor are 40.5 mm x 30.5 mm (LEM) or 40.5 mm x 40.5 mm (TAMURA).
  • Page 6: Installing An Adapter

    Installing an Adapter • Install an adapter if only the CIM communications cable connects to the UPS. • Prepare ST3.5x35 tapping screws, washers, and 6x30 plastic expansion sleeves by yourself. ST3.5x35 tapping screw Washer 6x30 plastic expansion sleeve ST3.5 0.3 N· m Installing Cables (ECC Scenario) System Networking This chapter uses the ECC scenario where the CIM communications cable connects to a smart ETH...
  • Page 7: Connecting Cables

    When a battery system needs to be managed by multiple CIMs, the CIMs can be connected to northbound devices through straight-through cables (the ECC supports four CIMs in parallel). Smart ETH gateway Connecting Cables • Connect the Hall effect sensor on the positive battery string terminal to the HALL_1 current monitoring port on the CIM, and connect the Hall effect sensor on the negative battery string terminal to the HALL_2 current monitoring port on the CIM.
  • Page 8 Installing Cables (UPS Scenario) System Networking This chapter uses the UPS scenario where the CIM power cable connects to an adapter, and the CIM communications cable connects to the UPS as an example to describe how to connect cables. If only the UPS is used, connect cables by following instructions in this section. AC input Adapter When a battery system needs to be managed by multiple CIMs, the CIMs can be cascaded...
  • Page 9 Connecting Cables 1. Connect the cable between the CIM and the Hall effect sensor. • If each of the positive and negative battery string cables connects to one Hall effect sensor, connect the Hall effect sensor on the positive battery string terminal side to the HALL_1 current monitoring port on the CIM, and connect the Hall effect sensor on the negative battery string terminal side to the HALL_2 current monitoring port on the CIM.
  • Page 10 2. Connect the CIM communications cable. • Prepare an RS485 cable by yourself. • The previous figure shows how to prepare an RS485 cable and a straight- through cable. UPS monitoring interface card (MUS05A) 3. Connect the cable between the UPS and the BIB. UPS dry contact card (MUE05A) Signal Port Mapping Between the UPS and...
  • Page 11 Socket Adapter 5. If multiple CIMs are cascaded, set the DIP switch by referring to the following table. Toggle Toggle Toggle Toggle Corresponding CIM Switch 1 Switch 2 Switch 3 Switch 4 Address in the (ADDR_1) (ADDR_2) (ADDR_3) (ADDR_4) Management System CIM1 CIM2 CIM3...
  • Page 12: Verifying The Installation

    Set parameters on the CIM WebUI, ECC WebUI, UPS WebUI, or UPS LCD based on the scenario to perform CIM and BIM networking. This document describes how to set parameters on the CIM WebUI. For details about how to set parameters on other UIs, see the iBAT 2.0-CIM01C2 User Manual. Prerequisites •...
  • Page 13 2. Open Internet Explorer, choose Tools > Internet Options > Advanced, and select Use TLS 1.1 and Use TLS 1.2. 3. Enter https://CIM IP address in the address box of Internet Explorer to log in to the iBOX WebUI home page. •...
  • Page 14 6. Access the System Settings page, and set the Time and IP Address parameters according to the following table. System Settings Description Time Set the local time zone, date, and time. Set the IP address, subnet mask, and default gateway of the iBOX. Set IP Address this parameter based on the IP address assigned by the administrator.
  • Page 15 For a data center, you are advised to set Batt. undervolt. Protect thres. to 1.6 V/cell. • If Batt low volt protection point cannot be set, check whether the BIM Comm. Failure alarm is generated. HUAWEI TECHNOLOGIES CO., LTD. Huawei Industrial Base, Bantian, Longgang Shenzhen 518129 People's Republic of China e.huawei.com...