1-10. Installation Procedure
2. Insert the processor board along the guide rail.
3. Tighten the upper and lower knobs one after the other several times, then insert the connector
completely until the connector is connected.
n
Be sure to tighten the two screws one after the other.
If one screw is tightened completely first, there is a possibility of damaging the connector or screw.
11. Turning on the power
1. Turn on the power of the external switchboard.
2. Open the lower front door of the FVS-1000, then turn on the breaker and the power switch.
[Reference]
Once the power is turned on, unless the power switch is turned off, ON/OFF of the power is possible
by only switching the breaker with the lower door closed.
Power switch
1-20
Processor board
Breaker