Platform stop

The platform is fitted with two platform stops installed beneath the bavetta (rear edge of platform). If neces-
sary, the platform stops can be moved sideways if they are e.g. in the way of the superstructure shute bolt.
4.6

Arm stops

If platform stops cannot be installed, they may be replaced by end stops between the lift arms and the vehi-
cle floor rear beam. The left and right end stops must be reached at the same time, as high as possible on
the left arm.
IMPORTANT!
Welding on the lift arm is not permitted. Installation must take place on the vehicle body.
4.5

Purging the cylinders

Purge the lift cylinders by lowering the platform all the way to the ground a few times. It may be necessary to
raise the vehicle to allow the platform to be lowered completely.
Purge the tilt cylinders by tilting the platform all the way up and then all the way down.
www.zepro.com
Picture 35. Platform stops are in-
stalled beneath the bavetta
Picture 34. Fit end stops between the lift arms
and the rear beam of the vehicle floor