Installation

4
Installation
4.1

Support frame

1. Carefully drive the slide function so the support frame is positioned as far back as possible.
2. Carefully raise the 1st booms to their highest position.
3. Raise the support frame to the trailer frame. A workshop jack is helpful. Measure the distance between
the 1st boom and the platform, see Picture 24.
Position in Y-axis: Adjust the angle of the arms by carefully running the lift up/down to attain the correct
dimensions in the Y-axis when all the attachment points of the tail lift bear on the trailer frame.
Position in X-axis: Install the slide profiles against the frame in position to attain the correct dimensions
in the X-axis. If necessary, the rearmost position of the frame can be adjusted forwards in the slide profile
with the help of the integrated adjustment for working position, see section 4.2.
4. Fit the support frame to the trailer frame using the clamping brackets. Tighten the screws (12x).
Tightening torque: 180 Nm.
IMPORTANT!
Welding is not permitted on the chassis brackets.
Do not run the lift all the way to the arm stops or with the platform fitted before all the bolts are fully
tightened against the chassis.
Do not load the lift until all bolts are tightened.
Do not load the lift before the bodywork is installed.
X= 94 mm (with 50 mm bavetta)
114 mm (with 70 mm bavetta)
20
Picture 24. Installation of support frame in the working position
ZT MK2
m
WARNING!
The friction plates are
an important part of
the underrun protec-
tion and must therefore
always be installed be-
tween the brackets and
the vehicle's chassis
beams.