2.7.2

Manifold operation

2-Valve and Block and Bleed Style Manifolds
Isolating the device
In normal operation the Isolate (block) valve between the process port and device will be
open and the Test/Vent valve will be closed. On a block and bleed style manifold, a single
block valve provides device isolation and a bleed screw provides drain/vent capabilities.
Isolate
12
Wrench tighten manifold into process connection (minimum toque value is
425 in-lbs).
Count how many threads are still showing (minimum engagement is 3
revolutions).
Subtract the number of threads showing (after tightening) from the total threads
to calculate the revolutions engaged. Further tighten until a minimum of 3
rotations is achieved.
For block and bleed manifold, verify the bleed screw is installed and tightened. For
2-valve manifold, verify the vent plug is installed and tightened.
Leak-check assembly to maximum pressure range of device.
Device
Process
(open)
Test/vent
(closed)
Reference Manual
00809-0100-4045, Rev AB