B≥1,000mm, make sure that the rear door of the cabinet can be fully opened. Ventilation and
heat dissipation should be ensured. Users can also have sufficient space for product
maintenance.
4.3.1.3 Cabinet Installation
After the cabinet is removed to the installation position with a forklift or a tool. The cabinet
should be adjusted and removed to the designed position. Then open the internal door of
cabinet, and fix the cabinet with M13 screws, as shown in Figure 4- 3.
When the cabinet needs to be fixed on the steel channel, Φ14 holes can be made in the steel
channel. Fix the cabinet to the steel channel with screws, as shown in Figure 4- 4.
Figure 4-4 Fix the cabinet to the steel
channel
When the cabinet is fixed to the concrete floor, make holes on the floor and fix the cabinet to
the concrete floor with expansion screws, as shown in Figure 4- 5.
______________________________________________________________________
Installation
Figure 4-3 Diagram of the cabinet base
Figure 4-5 Fix the cabinet to the
concrete floor
Alpha ESS Co., Ltd.
Your Smart Energy
Page 27 of 48

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Storion-t100

Table of Contents