COMMISSIONING

COMMISSIONING THE APPLIANCE FOR DIFFERENT GAS TYPE

230 VOLTS, RISK OF ELECTRICAL SHOCK!
Installation and commissioning MUST be carried out ONLY by an Authorised person.
WARNING
Wiring inside this appliance may be at 230V potential, when performing the commissioning, the
appliance electrical power will need to be connected. Exercise CAUTION as there is potential for
electric shock from the exposed wiring and circuitry. DO NOT leave the appliance unattended
when power is connected and the panels are removed.
This appliance is factory set for the correct gas type as per it's gas type labelling, re-commissioning for gas type will
only be required if the PCB is being replaced or if it has undergone a gas type conversion, i.e.; from NG to Propane
or vice versa. Commissioning of the gas is carried out via the PCB.
Commissioning of the PCB MUST be carried out BEFORE the gas pressures are checked.
NOTE
1.
Turn on the gas and power supply to the appliance.
2.
Press the 'UP' button or 'DOWN' button to obtain the correct gas type code for the appliance. Refer to chart
to below for the correct gas type code.
3.
With the appliance OFF, press the 'TEST' button, the gas type code will be shown on the display.
4.
Press the 'SET' button, to lock in the code.
5.
Gas pressure settings should now be checked as per "Checking and setting Pilot burner pressure" on page
28, Steps 1 through 3.
Rinnai
6
11
Natural Gas
A1
7
8
13
12
10
9
Propane Gas
L1
30
RDV 600_700ER IM