There are left and right rails on the H610S and H615C. Position the screw hole towards the
bottom so that the H610S/H615C thumbscrew can secure the chassis to the rail.
Install the node/chassis
You install the H410C compute node and H410S storage node in a 2U, four-node chassis. For H610C, H615C,
and H610S, install the chassis/node directly onto the rails in the rack.
Starting with NetApp HCI 1.8, you can set up a storage cluster with two or three storage
nodes.
Remove all the packing material and wrapping from the unit. This prevents the nodes from
overheating and shutting down.
•
H410C and H410S nodes
•
H610C node/chassis
•
H610S and H615C node/chassis
H410C and H410S nodes
Steps
1. Install the H410C and H410S nodes in the chassis. Here is a rear-view example of a chassis with four
nodes installed:
Need help?
Do you have a question about the HCI and is the answer not in the manual?