Installing The Ups + Bottom Cabling Cabinet; Installing Cabinets - Huawei UPS5000-H-1200 kVA User Manual

Hide thumbs Also See for UPS5000-H-1200 kVA:
Table of Contents

Advertisement

UPS5000-H-(1200 kVA-1600 kVA)
User Manual (100 kVA Power Modules)
Figure 6-42 Installing signal cables between the UPS and the SmartLi
(1) Monitoring interface unit in the master SmartLi cabinet
----End

6.2.4 Installing the UPS + Bottom Cabling Cabinet

Cables can be routed from the bottom if the optional bottom cabling cabinet is
configured.

6.2.4.1 Installing Cabinets

Installation on the Floor
Ensure that the installation floor is flat.
Step 1 Determine the cabinet installation positions on the floor based on the holes in the
marking-off template for floor installation.
Issue 03 (2021-04-22)
NO TICE
NO TE
● A: mounting holes on the channel steel
● B: mounting holes on the floor
Copyright © Huawei Technologies Co., Ltd.
6 Installation
90