GE CT ProSpeed Series Installation Manual page 147

Table of Contents

Advertisement

GE MEDICAL SYSTEMS
REV 11
5 1
PRECAUTION
Complete the Table Center Alignment before Anchoring the Gantry and Table.
Prior to anchoring, after drilling the anchoring holes, check that the Gantry and Table are tightly fixed
together by two bolts (Section 2-3,
CRASH HAZARD!! THE TABLE AND GANTRY MUST BE ANCHORED.
5 2
ANCHORING
Unstable condition. Keep the Table at its highest position. Don't tilt the Gantry.
Perform TABLE TO GANTRY ALIGNMENT as outlined in Section 2 of the System Adjustment tab of the Functional
Check/Adjustment manual.
Mark the anchoring positions and then move the system to drill the anchoring holes.
Anchor the CT system at five points: one for the Gantry, and four at the Table. Illustration 5-5 shows the possible
anchoring positions, choose the most appropriate locations.
The following hardware is provided with the system.
See Illustration 5-5.
6
Anchor bolts
6
Flat washers
6
Insulating Plates
6
Anchor Nuts and (Cone Wedges)
1
Anchor Stick
1.
During drilling, always keep the drill bit perpendicular to the floor.
2.
There is a gap between the channel base and the floor.
3.
Tighten the bolt with a torque of 40 kg-cm.
4.
The minimum Tensile load strength of the anchors must be 1000 kgf.
CT PROSPEED SERIES INSTALLATION
INSTALLATION AND LEVELING OF TABLE
DANGER!!
CAUTION
Note
5-3
2124011
).