4.8.2 Instructions

The instructions below detail how to set up the programmer to be powered at +5.0V from the Target
System.
1. Create a Programming Project which does NOT power the Target System
In EQTools – Project Builder – Select the <Target Power Supply Settings> tab
Set the 'Target Voltage' to +5.0V with a tolerance of +/- 500mV.
Set the 'Programmer Controlled Power Supply' to <Programmer controlled Target
Power Supply: OFF>
Leave all other settings as the default values.
2. Connect the programmer to the Target System
Connect the Target System to the programmer via an ISP Cable, Fast Connect connectors
or wire-wrap connectors.
Remove the 'Vcc Option Link' on the I/O Connector Module (labelled J6 or J28).
Check that you have a zero ohm connection between the Target Vcc (Vout) of the
programmer and the Vcc line of the Target System.
Using a DVM, check that there are no shorts between the Target_Vcc and Target Ground
3. Typical programming iteration
Power up the Target System
Using the keypad / display, select the required Programming Project
Press <Yes> key to execute Programming Project
Power down the programmer / Target System
70
the programmer powers up