Installation, continued
Under ceiling
installation
14
Please follow this below procedure for ceiling installation
Step
Action
1
The HCC 2 Alu should
always tilt minimum 1°
towards the drain side(T4).
This is achieved when us-
ing the enclosed bracket,
placed at T4 end of unit.
See more at page 10 as
well as on the label on the
front of the unit.
Drill two holes and mount
the bracket into the ceiling
configuration setup (see
page 13)
Please allow minimum 320
mm to the ceiling edge,
in order to have room for
turning the unit in step 2.
2
Lift the unit onto the
bracket hanging freely as
shown
3
Turn the unit towards the
ceiling, and secure it with
two screws
4
Connect drainage hose. See more at page 16.
Illustration
320 mm