4.3. Do not lift the machine before you are sure that the bearing knives of the equipments such as fork-lift come under the
machine when transferring the machine.
4.4. Movable parts on the machine should be fixed before carrying out the transport.
4.5. The machine size and weight measurements, given the technical specification sheet.

5. INSTALLATION OF THE MACHINE

5.1 Preparation

5.1.1 The machine size and weight measurements, given the technical specification sheet.The ground, where the
machine will be placed, should be even, solid enough to bear the weight of the machine
5.1.2 The machine should be located approx. 150 cm away from the rear wall
5.1.3 You can provide the balance of the machine with adjustable counterforts (PICTURE 2 NO 2) in the bottom part.
5.1.4 The safety apparatus should not be removed from its place before the machine is worked firstly.
5.1.5 The front control board is delivered disassembly not to be damaged during the transfer. Mount the front control
board to the place on the machine as seen in FIGURE 4
5.1.6 Fasten MKN 300 material supply conveyor given as Standard accesory onto the cutting unit to the right side
surface of the machine as seen in the Figure 5 by using the screws on the machine. Provide the conveyor
bobbins and machine top surface to be the same parallelism by using a sensitive and calibrated water gauge.
5.1.7 To use shaving manifolde, the absorbtion flowrate of air for dry chips has to be thought min.20m/sec. 28 m/sec
absobtion flowrate of air wet chips (>=%18 humidity) can be decided to operate the manifolde