5. INSTALLATION OF THE MACHINE

5.1 Preparation
5.1.1 The machine size and weight measurements, given the technical specification sheet.The ground, where the
machine will be placed, should be even, solid enough to bear the weight of the machine.
5.1.2 The machine should be located approx. 100 cm away from the rear wall.
5.1.3 You can provide the balance of the machine with adjustable counterforts (FIGURE – 2 NO.2 ) in the bottom part.
5.1.4 Fasten MKN 300 conveyor ( FIGURE – 1 NO.9 ) given as Standard accesory onto the cutting unit to the right
side surface of the machine as seen in the FIGURE – 1 by using the screws on the machine. Provide the
conveyor bobbins and machine top surface to be the same parallelism by using a sensitive and calibrated water
gauge.
5.1.5 Side protective covers ( FIGURE – 8 NO.206 / 207 ) are sent as demounted. Mount the covers as shown on the
FIGURE – 12.
5.1.6 To use shaving manifolde, the absorbtion flowrate of air for dry chips has to be thought min.20m/sec. 28 m/sec
absobtion flowrate of air wet chips (>=%18 humidity) can be decided to operate the manifolde.

5.2 Connecting to Power Source

5.2.1 The Electrical connection must be made by a licensed electrician.
5.2.2 The power outlet must be match with socket on the machine.
5.2.3 Plug the machine to a grounded socket.