5.1 Preparation

5.1.1 The machine size and weight measurements, given the technical specification sheet.The ground, where the
machine will be placed, should be even, solid enough to bear the weight of the machine.
5.1.2 The machine should be located approx. 50 cm away from the rear wall. The power connection plug of the
machine is located on the rear side of the machine.
5.1.3 You can provide the balance of the machine with adjustable counterforts (FIGURE 1 NO 1-1) in the bottom part.
5.1.4 Clamps (FIGURE 1 NO.75 / 88) are sent as demounted. Mount the clamps as shown on the figure on the table.
(FIGURE 1 NO.5)
5.1.5 Conditioner unit (FIGURE 1 NO.79) are sent as demounted. Mount the clamps as shown on the figure on the
chassis. (FIGURE 1 NO.1)
5.1.6 Plastic handle (FIGURE 1 NO.64) should be sent as demounted. Mount the plastic handle as shown on the
figure. (FIGURE 2 NO.63)
5.1.7 Make the MKN 300 conveyor (FIGURE 1 NO.86-optional) connection as in the FIGURE. The length of MKN 300
conveyor is 3 meters.
5.1.8 Remove the carriage safety part (FIGURE 2 NO.68). While removing the carriage safety part, head group that
the saw is connected is pushed to the rear side with the power of spring swiftly. This might cause severe
damage on machine. In order to prevent this situation, apply pressure on the arm that is enough to cover the