Installation
4*MC4
Figure 28 PV Wiring
Step 17: Close the battery covers and connect the PV-MC4 connectors to the system
(connection on both sides). Also, connect all AC cables, the meter communications
cable METER, and the Ethernet cable LAN. Then close the cable box cover.
The installation is now complete.
NOTE: the RCD unit must be installed. A 100mA RCD device is recommended.
Figure 29 DIP Operation
Step 18: Open the front cover of the last battery and remove the DIP cover. Now set
the DIP switch 2 to "on" mode and close the cover again.