Action
Check axial fan for:
•
Function
•
Running noise
•
Cleaning
Once the charging station has been switched on, the fans run for 15
minutes (test mode)
Change air filters on the bottom of the charging station
Check the RCCB (semi-annual DGUV V3) including protocol
Generate maintenance log
Function test for each individual charge point:
•
Trial charge (with commercial or electric vehicle)
•
Type 2 connector lock
•
Hinged cover control
Setup time
Indication of the next test date
Read out meter readings
Perform update
Change axial fan
Travel time
= Only for the option with a fixed charging cable
1
= Only for the option with an additional SCHUKO socket
2
SICHARGE Operating Instructions MID
Operating Instructions, 07/2020, A5E48573001-AB
A.2 Installation and maintenance schedule
Installa-
Commis-
tion/asse
sioning
mbly
x
x
x
x
x
x
x
When an update is available
In case of fan failure
x
x
Appendix
Mainte-
Duration
nance
in min.
x
2
x
4
x
14
x
15
x
10
x
10
x
2
x
2
2
20
x
99