Step 1 Turn on the single-phase power switch that controls the power supply from the remote
box-type transformer to the smart array controller.
Step 2 Turn on the three-phase power switch that controls the power supply from the remote
box-type transformer to the smart array controller.
Step 3 Check that the input voltages of all switches of the smart array controller are within
appropriate operating voltage ranges using a multimeter.
Step 4 Turn on the QF01 single-phase input switch on the smart array controller.
Step 5 Turn on the DC input and output switches on the smart array controller.
Step 6 Turn on the PID switch on the smart array controller.
Step 7 Turn on the three-phase input switch on the smart array controller.
----End
Follow-up Procedure

6.3 Closing the main Cabinet Door

Prerequisites
All components are running properly.
Issue 05 (2019-01-20)
If the smart array controller houses one PID module, turn on the appropriate three-phase
power switch.
If the smart array controller houses two PID modules, turn on the appropriate two
three-phase power switches.
If 24 V DC input and output are not used, skip this step.
If 24 V DC input is used, turn on the QF07 DC input switch.
If 24 V DC output is used, turn on the QF06 DC output switch.
If the smart array controller houses one PID module, turn on the QF03 PID switch.
If the smart array controller houses two PID modules, turn on the QF03 and QF05 PID
switches.
If the smart array controller houses one PID module, turn on the QF02 (or FU01)
three-phase input switch.
If the smart array controller houses two PID modules, turn on the QF02 and QF04 (or
FU01 and FU02) three-phase input switches.
Commission the PID module after powering it on. For the detailed commissioning
procedure, see the SmartPID2000 User Manual.
For details about the status of the energized SmartLogger2000 and PLC CCO as well as
the commissioning procedure, see the SmartLogger2000 User Manual.
The LAN switch can be directly put into use without commissioning after power-on.