• Level the machine so that all the supporting feet are taking the weight of the machine and no
rocking is taking place.

INSTALLATION

IMPORTANT:
Consider the following when looking for a suitable location to place the machine:
• Overall weight of the machine.
• Weight of material being processed.
• Sizes of material to be processed through the machine.
• Space needed for auxiliary stands, worktables, or other machinery.
• Clearance from walls and other obstacles.
• Maintain an adequate working area around the machine for safety.
• Have the work area well illuminated with proper lighting.
• Keep the floor free of oil and make sure it is not slippery.
• Remove scrap and waste materials regularly, and make sure the work area is free from
obstructing objects.
• If long lengths of material are to be fed into the machine, make sure that they will not extend
into any aisles.
• LEVELING: The machine should be sited on a level, concrete floor. Provisions for securing it
should be in position prior to placing the machine. The accuracy of any machine depends on
the precise placement of it to the mounting surface.
Horizontal Adjusting:
Placing the level at each point (the distance
between ends and points is 50mm. Adjust the
anchor bolt until the horizontal leveling
accuracy is within 0.2/1000mm.
Vertical Adjusting:
For the vertical direction of table has crowning (a
curve which treats the middle part as axis), you
must place gauge block on the table. Then put the
leveling rule on the gauge block; put the level on the
leveling rule. Adjusting the anchor bolt until the
vertical leveling accuracy is within 0.2/1000mm.