LOAD CELL WIRING TO JUNCTION BOX
The four (4) load cells are each wired to their respective terminals in the junction box according to the
corner numbering system shown in Figure 1 below. See Figure 2 on page 14 for junction box layout
and wiring connections. Tighten the strain relief hubs on the junction box with a wrench to assure proper
seal.
Figure 1: Load Cell Configuration
Figure 2: Junction Box Connections
Take the cable coming from the junction box of the 510 series and wire it to the indicator connector as
follows: