WARNING: DO NOT CUT THE LOAD CELL CABLE!
3. Pull the load cell cable out of the formed frame channels. The chase wire will be used to pull the
new load cell cable through the formed channel.
4. Install the new load cell by reversing the preceding steps. Reference the wiring diagram in Figure
3.
5. To verify correct load cell/junction box terminal matching, see the numbers on the terminals inside
the junction box and the corner numbering diagram in Figure 1: Load Cell Configuration.
6. Position load cells with load cell alignment arrow pointing up toward the deck. With the torque
wrench, tighten all mounting bolts to 75 ft. /lbs.
7. Route the load cell cables in each corner so that the cable is free from possible contact with the
load cell or load foot. Pull cable tight towards junction box, coil up extra length with cable ties and
securely store inside channel. (See figure 3, page 16)
8. Pass end of load cell cable through cable fittings in the NEMA 4X junction box.
Calibration is necessary after load cell replacement. Follow the calibration instructions in quick
reference in chapter 4.