PLC means Programmable Logical Controller. Our PLC is programmed
with specific programs to work with our equipment. Our programs are set
up for Valve filling, O/M net weigh and gross weighing equipment.
In the PLC, there are timers going to specific functions on the various types
of equipment which we factory set but need to be fined tuned in the field.
Below we discuss how to adjust the timers when you go to fine tuning
them.
Timer Adjustment Procedure for PLC
A Button is used to scroll through the Timers
B Button is used to scroll back
When you get to the function you want to adjust you will push the OK key to select that function. (When the time
is selected the numbers will flash on and off. When it is not selected blocks will flash over the time.)
Then use the + and – keys to adjust the timer up and down in 0.1 second increments.