ActiveScale™ X100 Support Guide
1. With the handle facing outward, align the replacement PSU with the empty slot.
2. Push the PSU into the server until there is an audible click.
3. Reattach the cord retention clip.
4. Reconnect the power cord.
5. Using UniverStor SM, verify that the PSU is functional.
a. In the UniverStor SM Dashboard, click the Resources tab.
b. In the system image on the Resources page, click the node with the degraded PSU. The node will
have an alert icon. The node's status page will appear.
c. Check that all of the PSU Icons listed under the PSU section do not have alert notifications.
Figure 3-45. PSU failure (left) and online PSU (right) icons
-
3.5.3 Replacing SFP+ 10G transceivers
Required tools
None
1
Note: The replacement procedure in this section applies to both sets of SFP+
transceivers.
3.5.3.1 Removing an SFP+ 10G transceiver
To replace the Storage Node SFP+ transceiver:
Personnel
~4 min