GE Agile P50 Series Technical Manual page 257

Compact feeder protection relay
Table of Contents

Advertisement

P50 Agile P153
Operating time
CB Fail
Operating time
I.
* Note : Filtering time (typically 25ms) is added when CBF initiated by external Binary input
Note:
As per IEC60255-151 clause 5.2 (assigned error 5%), the tolerances are calculated as below.
Value of characteristic quantity as multiple of setting value (Gs)
Limiting error as multiple of an assigned error
Percentage for time accuracy claim
Operating conditions
Relative humidity
I.
Operating temperature range
II.
Storage temperature range
III.
Terminals specification
AC current input terminals
I.
Auxiliary & input/output
II.
Terminals
Tightening torque for M4/M3
III.
screws
Rear communication terminal
IV.
Mechanical & Environmental specification
Design
I.
Weight
II.
Pollution Degree
III.
2.1.1
Standards Compliance
SR.
TYPE TEST
NO.
1.
Impulse, Dielectric and Insulation tests
1.1
Impulse voltage test
P153/EN M/B
IDMT characteristic shape
DT operation
** Reference condition
DT operation
CBF Reset
Reset current
Humidity (RH) 95% maximum
-25 ºC to +55 ºC
-25 ºC to +70 ºC
M3.5 threaded terminals for ring lug connection. Suitable up to 4 mm
M3 threaded terminal connection. Suitable up to 2.5 mm
Maximum torque of 0.6 Nm
Two wire connection. Suitable up to 2.5 mm
Flush mounting case
1.9 Kg approximate
II
STANDARD
Test voltage
Energy
Polarity
IEC 60255-27:2005
(incl. corrigendum 2007)
No. of impulses
Duration between impulses
EUT condition
13 Technical Specifications
As per clause 5.2 of IEC60255-151 or
50 ms whichever is greater
± 5% or 55 ms whichever is greater**
Currents applied at 2x pick-up level or
higher
± 5% or 55 ms whichever is greater
<40 ms*
Setting ± 10%
2-5
5-10
2.5
1.5
2
2
2
TEST SPECIFICATION/METHOD
5kv, 1.2/50 µV
0.5 J
+ve and –ve
3 on each polarity
5s
Non energised
Above 10
1