EasyLine EL3000 Series Commissioning Instructions

Gas Analyzer Start-Up

Starting Up the Gas Analyzer
NOTE
The notes in the sections "ZO23: Gas analyzer start-up (see page 95)"
and "Fidas24: Gas analyzer start-up (see page 96)" must also be
considered for the ZO23 and Fidas24 analyzers.
1
Switch on the power supply of the gas analyzer.
2
The name of the gas analyzer and the number of the software version
are shown in the display while booting.
3
After the start-up phase has ended, the display switches over to the
measured value display.
Example:
4
Check the configuration of the gas analyzer and alter if necessary.
5
After the warm-up phase has ended, the gas analyzer is ready to
carry out measurements.
Duration of the warm-up phase:
Uras26: approx. ½ hour without thermostat, approx. 2 hours with
thermostat
Limas23: approx. 2 hours
Magnos206: approx. 1 hour
Magnos27: approx. 2–4 hours
Caldos27: approx. ½ hour
Fidas24: approx. 2 hours
6
Check the calibration (see page 111) of the gas analyzer.
The gas analyzer is calibrated ex works. However, transport stresses
and the pressure and temperature conditions at the installation site
may influence the calibration.
7
Turn on the sample gas supply.