Gas analyzer start-up

Checking and approving for use

Performing a final
check of the analyzer
Checking the
environmental
conditions
Checking the
mechanical system
LS4000, LS4060 DIODE LASER ANALYZERS | OI/LS4000/O2-EN REV. A
Topic
Checking and approving for use ......................................................................153
Connecting the supply voltage ........................................................................ 156
Recognizing the operating status ................................................................... 156
Connecting the PC to the junction box ........................................................... 157
Connecting to the instrument software ........................................................ 158
Menu structure of the instrument software ................................................. 159
Main menu ........................................................................................................... 160
System time menu .............................................................................................. 161
Fine alignment of the purging flanges ........................................................... 162
Alignment menu.................................................................................................. 164
Installation procedure ....................................................................................... 165
Installation - Process parameters menu ....................................................... 166
Installation - Installation flanges menu ......................................................... 168
Installation - Ambient conditions menu ........................................................ 170
Installation - External inputs menu ................................................................. 171
Installation - Channels menu ............................................................................ 172
Installation - Analog and digital outputs menu ............................................ 173
Installation - Network settings menu ............................................................. 175
Installation - Save settings menu .................................................................... 176
Ensure that all pre-startup conditions are met.
Proceed in accordance with the following checklists:
Test object
Requirement
Transmitter unit,
The environmental conditions are consistent with the
receiver unit,
following information on the name plate:
junction box
 Zone
 Explosion group
 Temperature class
 Ambient temperature
Test object
Requirement
Junction box
The junction box meets the following requirements:
 The junction box is not damaged
 The junction box has been installed in a stable manner
 The junction box is closed so that no dust can penetrate
 All of the fixing screws on the housing cover are pre-
sent and securely tightened.