Barco ILite Installation Manual page 65

Rental display
Table of Contents

Advertisement

Image 7-41
5. Close the side locking mechanism of the rental tile at the adjoining side by rotating the handle of the side locking mechanism
360º clockwise.
Caution:
Never use adverse force to lock the mechanism.
Image 7-42
6. Repeat from step 1 until all truss beams are joined with each other.
After all truss beams are joined with each other you can proceed with installing the remaining ILite rental tiles
row by row.
After installing one or two rows of ILite rental tiles, realize the data and power cabling for these installed rows,
before lifting the rows further up. These rows are now easy accessible from the work floor.
R5976189 ILITE RENTAL DISPLAY 16/09/2005
360º
7. Basic setup procedures
61