Viessmann Vitobloc 200 EM-50/81 Operating Instructions Manual page 29

Block-type thermal power plant module for natural gas operation
Table of Contents

Advertisement

Commissioning
10. Check the connection of the emergency shut-
down.
11. Check the connection for general faults.
12. Check the connection of the fault in the heat-
ing water pump.
13. Check the connection of the request "Heating
water pump ON".
14. Check the connection of the potential-free
messages (according to client's request).
15. Remove fuse 12F1 (alternator contactor 12K4
cannot be activated)
16. Connect the battery.
17. Switch on the external power input into the
network and the external measuring-circuit
voltage, if power stand-by operations are
planned.
18. Check the rotating field of the network and of
the measuring-circuit voltage.
19. Switch on all fuse and circuit-breakers.
20. Check the rotating field and the potential
equality of the measuring-circuit voltage.
21. Acknowledge and eliminate any pending fault
messages.
22. Connect the U column to the zero pressure
regulator and the compensation line.
23. Open the gas cock and start the module in the
manual mode.
24. Check the ignition moment and the setting of
the zero pressure regulator with the engine
idling.
25. Check the rotating field of the alternator.
26. Check the rotating field and the potential
equality of the alternator voltage.
27. Adjust the alternator voltage, if necessary.
VITOBLOC 200 Operating instructions for the natural gas-fuelled CHP module
- switching diagram, sheet 18
- module control panel:
internal or external overtemperature protector switch, external
gas detector, fire alarm etc. to -X1/22.23, if not existing bridge
to -X1/22.23.
- switching diagram, sheet 19
- module control panel:
general breakdown to -X1/26.27, if not existing bridge to -
X1/26.27.
- switching diagram, sheet 18
- module control panel:
heating water pump broken down to -X1/28.29, if not existing
bridge to -X1/28.29.
- switching diagram, sheet 23
- module control panel:
request "Heating water pump ON" to -X5/9.10.
- switching diagram, sheet 23
- module control panel: potential-free messages connected to -
X5 in accordance with client's request
- module control panel
- check, whether bridge between both batteries is firm
- connect negative terminal last.
- switch on on-site master switch or on-site mains fuse
- module control panel
- check rotating field of network at -1F1 and the measuring-
circuit voltage at -1F3
- module control panel
- switching diagram, sheet 2
- module control panel
- check rotating field and potential equality of the measuring-
circuit voltage at voltage cards L1N. L2N. L3N.
- display and operator's unit of the module control: LED display
(red) of the error message.
- establish and rectify the cause of the fault according to section
4.8
- zero pressure regulator in the controlled system for the gas
- compensation line downstream of the air filter
- display and operator's unit at the module control: manual
mode menu at level 2 (see section 4.4).
- ignition control at the rear of the module, inside to the left of
the extract air ventilator
- module control panel
- check the rotating field of the alternator at the alternator con-
tactor 12K4
- switching diagram, sheet 2
- module control panel
- check the rotating field and the potential equality of the alter-
nator voltage at the voltage cards L1G. L2G. L3G
- upper alternator terminal box: voltage regulator: P1
29