Page 3
5.10 Third Party Intellectual Property Rights. The Firmware may contain components transfer the Firmware directly to a third party only in connection with the sale of the Eaton (including open source software components) that are owned by third parties (“Third Party product in which it is installed.
6 6 O O p p e e r r a a t t i i o o n n ............................................................4 4 9 9 6.1 Control Panel Functions ..........................49 6.1.1 Changing the Language........................49 6.1.2 Display Functions ..........................49 6.1.3 User Settings............................. 50 Eaton 9355 Parallel UPS (10/15 kVA) User's Guide 164201601—Rev E0...
Page 6
8 8 W W a a r r r r a a n n t t y y ............................................................6 6 1 1 Eaton 9355 Parallel UPS (10/15 kVA) User's Guide 164201601—Rev E0...
Page 7
L L i i s s t t o o f f F F i i g g u u r r e e s s Figure 1. The Eaton 9355 UPS and EBM (3-High Cabinets Shown) ................ 1 Figure 2.
Page 8
Version 2 Bypass Cabinet Bypass Wiring Diagram – with MIS..............47 Figure 44. Version 2 Tie Cabinet Parallel UPS Schematic..................48 Figure 45. Eaton 9355 UPS Control Panel ......................49 viii Eaton 9355 Parallel UPS (10/15 kVA) User's Guide 164201601—Rev E0...
Page 9
UPS Cabinet Weights ........................10 Table 3. UPS Cabinet Clearances ......................... 11 Table 4. Eaton 9355 10–15 kVA Parallel UPS: Recommended Terminal Block Wiring ..........12 Table 5. Menu Map for Display Functions ...................... 50 Table 6. User Settings..........................51...
Chapter 8 Warranty for details. This service is offered as part of the sales contract for the UPS. Contact an Eaton service representative in advance (a minimum two-week notice is required) to reserve a preferred startup date. Figure 1. The Eaton 9355 UPS and EBM (3-High Cabinets Shown)
Page 12
U U s s i i n n g g T T h h i i s s M M a a n n u u a a l l This manual describes how to install and operate the Eaton 9355 UPS. Read and understand the procedures described in this manual to ensure trouble-free installation and operation.
F F o o r r M M o o r r e e I I n n f f o o r r m m a a t t i i o o n n Refer to the Eaton 9355 UPS 10/15 kVA User’s Guide for the following additional information: •...
Page 14
E E q q u u i i p p m m e e n n t t R R e e g g i i s s t t r r a a t t i i o o n n Please visit www.eaton.com/pq/register to register your new Eaton UPS / Eaton UPS Accessory. Model Number: Serial Number:...
Page 15
• Proper disposal of batteries is required. Refer to your local codes for disposal requirements. • Never dispose of batteries in a fire. Batteries may explode when exposed to flame. Eaton 9355 Parallel UPS (10/15 kVA) User's Guide 164201601—Rev E0...
Page 16
Une mise au rebut réglementaire des batteries est obligatoire. Consulter les règlements en vigueur dans votre localité. • Ne jamais jeter les batteries au feu. L'exposition aux flammes risque de les faire exploser. Eaton 9355 Parallel UPS (10/15 kVA) User's Guide 164201601—Rev E0...
Page 17
Es necesario desechar las baterías de un modo adecuado. Consulte las normas locales para conocer los requisitos pertinentes. • Nunca deseche las baterías en el fuego. Las baterías pueden explotar si se las expone a la llama. Eaton 9355 Parallel UPS (10/15 kVA) User's Guide 164201601—Rev E0...
Page 19
The system must be installed on a level floor suitable for computer or electronic equipment. • The system must be operated at an altitude no higher than 1500m (5000 ft) without derating. For additional assistance with high altitude operation, contact an Eaton service representative (see paragraph 1.5 Getting Help).
From Right of Cabinet Refer to local codes for right side service access [minimum 36" (91.4 cm)] For UPS cabinet and Extended Battery Module cabinet dimensions and center of gravity, see Eaton 9355 10/15 kVA UPS User’s Guide. 3 3 . . 3 3...
4 4 . . 2 2 . . 1 1 T T h h r r e e e e - - H H i i g g h h C C a a b b i i n n e e t t s s o o r r T T w w o o - - H H i i g g h h E E B B M M s s To remove a three-high cabinet or a two-high EBM from the shipping pallet: Remove the two M10 bolts securing the stabilizing bracket to the pallet (see Figure Eaton 9355 Parallel UPS (10/15 kVA) User's Guide 164201601—Rev E0...
Hold the back of the cabinet so that the bolts can be removed easily without the cabinet rolling backward. Remove the two M10 bolts securing the front shipping bracket and remove the bracket. If needed, adjust the leveling feet to release the bracket. Eaton 9355 Parallel UPS (10/15 kVA) User's Guide 164201601—Rev E0...
Slowly roll the cabinet toward the rear of the pallet. Once the pallet tilts, continue rolling the cabinet down the pallet until the cabinet touches the floor (see Figure If needed, adjust the leveling feet so that the cabinet rolls freely. Eaton 9355 Parallel UPS (10/15 kVA) User's Guide 164201601—Rev E0...
Remove the M10 bolt securing the vertical bracket to the pallet (see Figure Remove and retain the three M4 screws securing the vertical bracket to the UPS. Remove the vertical bracket. Eaton 9355 Parallel UPS (10/15 kVA) User's Guide 164201601—Rev E0...
Remove the three M10 bolts securing the rear shipping pad to the pallet and remove the shipping pad (see Figure NOTE Hold the back of the cabinet so that the bolts can be removed easily without the cabinet rolling backward. Eaton 9355 Parallel UPS (10/15 kVA) User's Guide 164201601—Rev E0...
10. Slowly roll the cabinet toward the rear of the pallet. Once the pallet tilts, continue rolling the cabinet down the pallet until the cabinet touches the floor (see Figure If needed, adjust the leveling feet so that the cabinet rolls freely. Eaton 9355 Parallel UPS (10/15 kVA) User's Guide 164201601—Rev E0...
E E x x t t e e r r n n a a l l A A C C P P o o w w e e r r W W i i r r i i n n g g I I n n s s t t a a l l l l a a t t i i o o n n You are now ready to install the Eaton 9355 UPS. Select one of the following installation options according to your UPS configuration: •...
NOTE To accommodate the feature of easy system expandability, it is recommended that initial installation of the Eaton 9355 UPS contain wiring to support the maximum capacity of the UPS cabinet. Switch off utility power to the distribution point where the parallel tie cabinet and UPSs will be connected.
10. Verify that each UPS battery circuit breaker is in the OFF position (see Figure 14). 11. From each UPS, remove the UPS wiring access cover and one of the conduit landing plates and retain. Eaton 9355 Parallel UPS (10/15 kVA) User's Guide 164201601—Rev E0...
Input neutral must be wired for proper operation. Failure to connect an input neutral will void the warranty. If the optional input transformer is installed, an input neutral is not required. NOTE 2 The Eaton 9355 UPS is a single-feed UPS only. Eaton 9355 Parallel UPS (10/15 kVA) User's Guide 164201601—Rev E0...
Connect the black and the red wire to TB2 on the UPS. Cap the blue wire. NOTE The maintenance bypass contacts are normally-open. To ensure proper bypass operation, DO NOT use the blue wire (it is normally-closed). Eaton 9355 Parallel UPS (10/15 kVA) User's Guide 164201601—Rev E0...
Figure 17. Version 1 Load Connections Maintenance Bypass Wiring to UPS TB2 Ground Neutral Line 1 Line 2 Line 3 19. Wire the AC input to the bypass breaker (see Figure 18). Eaton 9355 Parallel UPS (10/15 kVA) User's Guide 164201601—Rev E0...
To hardwire the parallel system: Verify that the electrical connections to the installation site have been properly installed. A wall-mounted, user–supplied, readily–accessible disconnection device must be incorporated in the input wiring. Eaton 9355 Parallel UPS (10/15 kVA) User's Guide 164201601—Rev E0...
NOTE To accommodate the feature of easy system expandability, it is recommended that initial installation of the Eaton 9355 UPS contain wiring to support the maximum capacity of the UPS cabinet. Switch off utility power to the distribution point where the parallel tie cabinet and UPSs will be connected.
UPS System Installation Figure 20. Version 2 Parallel Tie Cabinet Front Cover Open Internal Cover Front Cover Remove the internal cover to gain access to the breakers (see Figure 21). Eaton 9355 Parallel UPS (10/15 kVA) User's Guide 164201601—Rev E0...
® Verify that the parallel bypass breaker is in the OFF position (see Figure 22). 10. Mount the parallel tie cabinet to the wall and install the conduit. Eaton 9355 Parallel UPS (10/15 kVA) User's Guide 164201601—Rev E0...
12. From each UPS, remove the UPS wiring access cover and one of the conduit landing plates and retain. 13. Punch two holes in the conduit landing plate for the input and output conduit using a Greenlee punch or similar device. Eaton 9355 Parallel UPS (10/15 kVA) User's Guide 164201601—Rev E0...
Input neutral must be wired for proper operation. Failure to connect an input neutral will void the warranty. If the optional input transformer is installed, an input neutral is not required. NOTE 2 The Eaton 9355 UPS is a single-feed UPS only. Eaton 9355 Parallel UPS (10/15 kVA) User's Guide 164201601—Rev E0...
UPS System Installation Figure 24. UPS Terminal Block (3-High Shown) Maintenance Bypass Contacts Ground 15. Hardwire the output terminations from the UPS to the parallel tie cabinet (see Figure 25). Eaton 9355 Parallel UPS (10/15 kVA) User's Guide 164201601—Rev E0...
DO NOT use the blue wire (it is normally-closed). 18. Replace the UPS wiring access cover and conduit landing plate. 19. Repeat Step 13 through Step 18 for each UPS. Eaton 9355 Parallel UPS (10/15 kVA) User's Guide 164201601—Rev E0...
Figure 26. Version 2 Tie Cabinet Load Connections Line 1 Line 2 Line 3 Neutral Ground Maintenance Bypass Wiring to UPS TB2 20. Wire the AC input to the bypass breaker (see Figure 27). Eaton 9355 Parallel UPS (10/15 kVA) User's Guide 164201601—Rev E0...
This section describes the Powerware Hot Sync CAN Bridge Card. For other options, such as additional X-Slot cards, LanSafe Power Management Software, remote emergency power-off (REPO), relay output contacts, or programmable signal inputs, refer to the Eaton 9355 UPS (10/ 15 kVA) User's Guide.
Remove the front covers of all cabinets, starting with the top cabinet. Press and release the handle latch at the bottom of each cover and then lift the cover up and off the cabinet (see Figure 30). Eaton 9355 Parallel UPS (10/15 kVA) User's Guide 164201601—Rev E0...
UPS, the remaining UPS transfers the load to bypass instead of supporting the load. Verify all CAN Bridge Card wiring is correct for proper operation NOTE Signal Input 2 can still be used for building alarms; it is automatically rerouted to the CAN Bridge Card. Eaton 9355 Parallel UPS (10/15 kVA) User's Guide 164201601—Rev E0...
On the bottom cover (and also the middle cover if 3-high), remove a knockout tab in the top edge of the cover for each cable: With wire cutters, cut either side of the tab and twist down to remove the tab (see Figure 32). Eaton 9355 Parallel UPS (10/15 kVA) User's Guide 164201601—Rev E0...
UPS installation. NOTE After UPS startup, ensure maximum battery runtime by configuring the UPS for the correct number of EBMs (see paragraph 6.3 Configuring the UPS for EBMs). Eaton 9355 Parallel UPS (10/15 kVA) User's Guide 164201601—Rev E0...
4 4 . . 3 3 . . 4 4 S S t t a a b b i i l l i i z z i i n n g g t t h h e e C C a a b b i i n n e e t t NOTE 1 For seismic installations, you MUST order and install an Eaton 9355 UPS seismic kit; do not use the following instructions.
Plug the EBM cable into the UPS battery connector. If additional EBMs are installed, plug the EBM cable of the second cabinet into the battery connector on the first EBM. Repeat for each additional EBM. Eaton 9355 Parallel UPS (10/15 kVA) User's Guide 164201601—Rev E0...
UPS. NOTE After UPS startup, ensure maximum battery runtime by configuring the UPS for the correct number of EBMs (see paragraph 6.3 Configuring the UPS for EBMs). Eaton 9355 Parallel UPS (10/15 kVA) User's Guide 164201601—Rev E0...
Wires Auxiliary Contacts (common) Blue Wires (closed when breaker is open) 225A Bypass Input 110A (4X) 80A (4X) LOAD From UPS 1 Output 225A Not Used Not Used Not Used Eaton 9355 Parallel UPS (10/15 kVA) User's Guide 164201601—Rev E0...
C C h h a a p p t t e e r r 6 6 O O p p e e r r a a t t i i o o n n This chapter contains information on how to use the Eaton 9355 UPS, including front panel operation, UPS Removing the Existing Power Cords startup and shutdown, and configuring the UPS for Extended Battery Modules (EBMs).
As the default or after 15 minutes of inactivity, the LCD displays the As the default or after 15 minutes of inactivity, the LCD displays the selectable startup screen. The default is the Eaton logo and can be selectable startup screen. The default is the Eaton logo and r after 15 minutes of inactivity, the LCD displays the selectable startup screen.
Automatic Battery Tests Enabled Enabled/Disabled Enabled automatically runs the battery test once a month. Full Power Battery Test Enabled/Disabled Enabled Number of Battery Strings 0 through 22 2 strings for UPS-32 models Eaton 9355 Parallel UPS (10/15 kVA) User's Guide 164201601—Rev E0...
See Chapter 8 Warranty for details. This service is offered as part of the sales contract for the UPS. Contact an Eaton service representative in advance (a minimum two-week notice is required) to reserve a preferred startup date. WARNING Only qualified service personnel (such as a licensed electrician) should perform the UPS installation.
Page 63
Only qualified service personnel (such as a licensed electrician) should perform the UPS installation. Initial startup must be performed by an authorized Eaton Customer Service Engineer. Risk of electrical shock. Verify that UPS installation has been carried out correctly and the UPS ground has been connected.
Page 64
As the default or after 15 minutes of inactivity, the LCD displays the screen. screen. Display Functions selectable startup screen. The default is the Eaton logo and can be to ensure consistent runtimes. selectable startup screen. The default is the Eaton logo and can be Display Functions changed to the Mimic screen in the User Settings menu.
Page 65
As the default or after 15 minutes of inactivity, the LCD displays the p screen. The default is the Eaton logo and can be selectable startup screen. The default is the Eaton logo and can be UPS + 3 EBMs Mimic screen in the User Settings menu.
As the default or after 15 minutes of inactivity, the LCD displays the selectable startup screen. The default is the selectable startup screen. The default is the Eaton logo and can be changed to the Mimic screen in the User Se...
15 minutes of inactivity, the LCD displays the Verify that the maintenance isolation breaker (if present) on the Tie artup screen. The default is the Eaton logo and can be The UPS is now powering the load in Bypass mode.
C C h h a a p p t t e e r r 7 7 T T r r o o u u b b l l e e s s h h o o o o t t i i n n g g OPERATION The Eaton 9355 UPS is designed for durable, automatic operation and also alerts you whenever potential operating problems may occur. Usually the alarms shown by the control panel do not mean that the output power is affected.
Page 70
Display Functions Reset the REPO switch and restart the UPS. Verify that selectable startup screen. The default is the Eaton logo and can be selectable startup screen. The default is the Eaton logo and can be switch is active or the REPO connector is the REPO connector is present.
Page 71
C C h h a a p p t t e e r r 8 8 W W a a r r r r a a n n t t y y For warranty information, please refer to the Resources link on our website, www.eaton.com/9355.