Unpacking; Ups Clearance - Toshiba 5000 Series Installation And Operation Manual

Industrial ups. 3-phase, 480vin - single phase, 120vout
Hide thumbs Also See for 5000 Series:
Table of Contents

Advertisement

8.2

Unpacking

The UPS should be as close as possible to its final storage location. Allow enough space for forklift operations to unpack the
UPS crate. Then remove the crate.
Points to observe
Retain all small articles during unpacking and installation.
Make sure that exterior paint is not scratched and that the UPS cabinet is not damaged.
DO NOT damage the UPS when using tools to remove packaging materials.
If provided, DO NOT remove the plastic sheet cover, until installation.
Do not remove the fan covers until UPS start up. The fan covers should be removed by factory authorized
personnel. Packing materials should be disposed by the appropriate means.
Immediately report any abnormalities to Toshiba Customer Support Center or an authorized representative.
8.3

UPS Clearance

Maintain the indicated clearance during installation.
NOTE: Minimum front clearance when physically accessing the UPS must be at least the width of the front door of the UPS,
or per NEC 110.34(A)(36 in./900 mm) and local requirements, whichever is greater.
The 5000 Series 3P1 is front-access for installation, operation, and maintenance, wiring and cable installation. The clear-
ance around the UPS is listed in
CONFIGURATION
UPS & MBS
36 in. (914 mm)
5000 Series 3P1 Industrial UPS Installation and Operation Manual – 92973-001
Table
8.1.
TABLE 8.1: 5000 SERIES CLEARANCE REQUIREMENTS
5000 SERIES CLEARANCE REQUIREMENTS
FRONT
LEFT SIDE
3 in. (76.25 mm)
RIGHT SIDE
BACK
0 in. (0 mm)
0 in. (0 mm)
TOP
23 in. (584 mm)
25