Toshiba 5000 Series Installation And Operation Manual page 20

Industrial ups. 3-phase, 480vin - single phase, 120vout
Hide thumbs Also See for 5000 Series:
Table of Contents

Advertisement

The 5000 Series Industrial Duty UPS has a C-channel skids base with fork guides for font/back forklift access, Fork Slots
in the C-Chanel skids alowing forklift access from the side, and four lifting eyes for hoisting. The skids are bolted to the
shipping pallet to secure the UPS during shipping. Follow the directions below to unpack the UPS. Note that the 50kVA
5000 Series 3P1 consists of two sperate pallets with one large section and one smaller section. The 30kVA and 15kVA units
consist of only one pallet. 30kVA is the same size as the large section and 15kVA is the same size as the small section.
TOP HEAVY EQUIPMENT. THIS EQUIPMENT WILL TIP OVER EASILY UNTIL FIXED
IN PLACE.
Lift and move carefully, and only with adequate equipment and trained personnel.
IMPROPER LIFTING CAN RESULT IN INJURY OR DEATH.
Carefully inspect the UPS for shipping damage.
2
FIGURE 4.2: UNPACKING SMALL ENCLOSURE – 50/40KVA MBS & I/O CABINET OR 15KVA UPS
10
CAUTION
1. Remove shrink wrap.
2. Unbolt the UPS base from the
3. Use a forklift or crane to lift the
4. Put down the UPS and remove
5. Use a forklift or crane to transport the UPS to it's
installation location. See Section 8.
5000 Series 3P1 Industrial UPS Installation and Operation Manual – 92973-001
shipping pallet.
UPS off the shipping pallet.
the pallet.
3
4

Advertisement

Table of Contents
loading

Table of Contents