DO NOT transport, move, store, or place the UPS on its side.
Excessive force applied from heavy components inside may damage the UPS.
Avoid vibration or shock exceeding 0.5 g.
Failing to observe this precaution may cause damage to the UPS.
DO NOT allow the UPS to suffer shock or impact when unpacking.
Tools used to remove packaging materials may cause damage to the UPS.
DO NOT install the UPS in environments unsuitable for a NEMA-3R enclosure.
Submersion may cause electrical shock, personal injury or UPS failure.
DO NOT push or pull on the sides of the packaging or the UPS to move it.
Always use a crane, forklift, or pallet jack for transporting and positioning the
UPS.
Pushing/pulling on the sides of the unit to move it may result in damage to the UPS.
4

Unpacking

4.1

General Instructions

The UPS should be as close as possible to its final location when unpacking. Allow enough space for forklift/
crane operations to unpack the UPS from the packing crate. Then remove the crate. Properly dispose of
the crate.
Points to observe:
Retain all small articles during unpacking and installation.
Examine the UPS cabinet to ensure that it is not damaged and no paint is scratched before
uncrating.
Take precaution to not damage the UPS when using tools to remove packaging materials.
If provided, DO NOT remove the protective plastic sheet cover until installation at final location.
Immediately report any cabinet abnormalities to Toshiba Customer Support Center or an
authorized representative.