Unpacking the new UPS equipment 15/25/30 kVA:

Upon receipt of the UPS, a careful inspection for shipping damage should be made. Units
shipped within North America are shrink-wrapped; those outside North America are crated.
2. Unbolt the rails from both the unit
and the shipping pallet.
Place the rails on the front of
the pallet.
Use the four 1/2 x 3" bolts to
secure the rails to the shipping
pallet.
Attach the rails as shown in the
front to the front of the pallet.
DANGER
10
TOSHIBA
1. Remove packing material.
1a. For international units,
remove the screws that
attach the shipping crate
to the pallet.
Remove the crate and
foam packing material.
TOP HEAVY EQUIPMENT. IMPROPER LIFTING CAN RESULT IN INJURY OR
DEATH. LIFT AND MOVE CAREFULLY AND ONLY WITH ADEQUATE
EQUIPMENT AND TRAINED PERSONNEL. THIS EQUIPMENT WILL TIP OVER
EASILY UNTIL FIXED IN PLACE.
3. Place the tie brackets in the slots at
the lower end of the ramps.
SLOWLY roll the unit down the
ramp.