Step 5 - Configure Day Mode Operation (If Required); Step 6 - Configure Network Options (If Required); Step 7 - Commence Normal Operation - Honeywell Morley-IAS ZX Series Commissioning Manual

Fire alarm control panels
Table of Contents

Advertisement

MORLEY-IAS
Finally, select the INSPECT option from page 1 of the Commission Menus. Compare the
commissioning data entered against the installation sheets. This facility allows the data to be
inspected without risking any inadvertent changes.
4.5 Step 5 – Configure Day Mode Operation (If required)
EN54-2 7.11
EN54
Delays to Outputs
!
4.6 Step 6 – Configure Network Options (If required)
Select the 'NETWORK' option from page 3 of the Commission Menus. Press 'Yes' to step through
each item to inspect the factory default settings and change as required. For example, panel address,
number of slave panels, etc.
4.7 Step 7 – Commence Normal Operation
Before finally commencing normal operation, perform the following.
1.
Select 'PASSWORDS' from page 2 of the Commission Menus. Set the number of Level 2 passwords
and define the value of each password.
2.
Select 'PROGRAM INTEGRITY' from page 2 of the Commission Menus. Check and record the
program checksums.
Select 'NORMAL OPERATION' from page 1 of the Commission Menus.
Remember to lock the memory!!!
Page 14
Select the DAY MODES option from Page 3 of the
Commission Menus and then perform the following.
1.
Select 'Delayed Mode', if the sounders and outputs are to be
delayed. (NOTE: Must be enabled at Level 2 to activate).
2.
Select 'Sensitivity Mode', if the detectors are to have different
pre-alarm and fire alarm settings during day / night.
3.
Select 'Verification Mode', if the analogue signals are to be
verified before the panel registers a fire alarm.
Program the required mode as required.