To wire the controller for power

Remove power from the power supply.
1
Pull the screw terminal connector from the controller's power terminals labeled Gnd and 24 Vac or Hot.
2
Connect the transformer wires to the screw terminal connector.
3
Apply power to the power supply.
4
Measure the voltage at the VVT Zone Controller's power input terminals to verify that the voltage is within
5
the operating range of 21.6–26.4 Vac.
Connect a 4-inch (10.2 cm) wire from Gnd to the control panel.
6
Insert the screw terminal connector into the VVT Zone Controller's power terminals.
7
Verify that the Power LED is on and the Run LED is blinking.
8

To address the VVT Zone Controller

You must give the VVT Zone Controller an address that is unique on the network. You can address the VVT
Zone Controller before or after you wire it for power.
If the VVT Zone Controller has been wired for power, pull the screw terminal connector from the
1
controller's power terminals labeled Gnd and 24 Vac. The controller reads the address each time you
apply power to it.
Using the rotary switches, set the controller's address. Set the Tens (10's) switch to the tens digit of the
2
address, and set the Ones (1's) switch to the ones digit.
EXAMPLE If the controller's address is 25, point the arrow on the Tens (10's) switch to 2 and the arrow
on the Ones (1's) switch to 5.
0
0
CAUTION The factory default setting is "00" and must be changed to successfully install your VVT Zone
Controller.
VVT Zone Controller
10's
1's