Visual Inspection - ABB RET670 Commissioning Manual

Transformer protection version 2.1 ansi
Hide thumbs Also See for RET670:
Table of Contents

Advertisement

Section 13
Commissioning and maintenance of the fault clearing system
13.2.1

Visual inspection

Prior to testing, the protection IEDs should be inspected to detect any visible damage that may
have occurred (for example, dirt or moisture deposits, overheating).
Make sure that all IEDs are equipped with covers.
13.2.2
Maintenance tests
To be made after the first half year of service, then with the cycle as proposed above and after any
suspected maloperation or change of the IED setting.
Testing of protection IEDs shall preferably be made with the primary circuit de-energized. The IED
cannot protect the circuit during testing. Trained personnel may test one IED at a time on live
circuits where redundant protection is installed and de-energization of the primary circuit is not
allowed.
ABB protection IEDs are preferably tested by aid of components from the COMBITEST testing
system or FT test systems described in information B03-9510 E. Main components are RTXP
8/18/24 test switch usually located to the left in each protection IED and RTXH 8/18/24 test
handle, which is inserted in test switch at secondary testing. All necessary operations such as
opening of trip circuits, short-circuiting of current circuits and opening of voltage circuits are
automatically performed in the right order to allow for simple and safe secondary testing even
with the object in service.
Important components of FT test system are FT1, FTx, FT19, FT19RS, FR19RX switches and
assemblies as well as FT-1 test plug.
13.2.2.1
Preparation
Before starting maintenance testing, the test engineers should scrutinize applicable circuit
diagrams and have the following documentation available:
Test instructions for protection IEDs to be tested
Test records from previous commissioning and maintenance tests
List of valid settings
Blank test records to fill in measured values
228
First maintenance test should always be carried out after the first half year of
service.
When protection IEDs are combined with built-in control, the test interval can be
increased drastically, up to for instance 15 years, because the IED continuously
reads service values, operates the breakers, and so on.
1MRK 504 154-UUS B
SEMOD56525-5 v3
SEMOD56534-1 v1
SEMOD56528-5 v5
SEMOD56528-10 v2
Commissioning manual