Commissioning the drive
5.1 Configuring the drive
4. Confirm the following question with "OK", in order to perform an NCK Power On Reset.
5. After the system has been powered-up, you receive the following message:
6. Confirm with "OK".
7. The configuration has been completed once the topology data has been determined.
92
This can take several minutes.
Figure 5-4
Confirming the Power On Reset
Figure 5-5
Completing the automatic configuration
The commissioning software for SINAMICS S120 (Page 13) is required on the PG/PC for
the next commissioning steps.
Commissioning Manual, 02/2012, 6FC5397-3DP40-3BA0
Turning and Milling