3.5. Operation Test and Installation Instruction

3.5.1.
Start Up in Normal Mode
3.5.1.1.
Open the terminal block cover on the rear panel (refer to 2.3.2) Before
start the installation, please make sure the grounding is connected
properly.
Make sure Utility breaker, UPS' Utility breaker and Bypass breaker are
3.5.1.2.
On "Off" position.
3.5.1.3.
Make sure the voltage of Utility matches with the input voltage window of
the UPS.
Connect the Utility separately to the terminal blocks of UPS' Utility and
3.5.1.4.
Bypass Inputs. Switch on the Power Breaker of the distribution panel
and the breakers of the UPS' Utility and Bypass Inputs, and then the
UPS starts up. Green LEDs
Bypass Inputs are normal and the LCD display with parallel function will
illustrate from drawing A1, drawing A2 to drawing B. Otherwise the LCD
display will illustrate from drawing A2 to drawing B.
A1.
A2.
B.
&
light up to show the Utility and
18