Pylontech PowerCube-H1 Operation Manual page 17

Lithium-ion phosphate energy storage system
Hide thumbs Also See for PowerCube-H1:
Table of Contents

Advertisement

OFF.
Warning: MBMS must be turned on after all battery strings self-check finish.
(1) Check the UPS is turned on and suppling power if configured.
(2) Switch the external power or PCS on, to make sure all the power equipments can work
normally.
(3) Turn on the 1
The second BMS must be operated after the first battery string's self-check is successful.
From 1st BMS to the last BMS Then turn on the battery strings on one by one.
Turn on the "POWERRELAY SWITCH":
Warning: This Power Relay Switch must be sure turned ON. Otherwise it will affect
automatic checking process and causes danger.
Turn on the "POWER SWITCH":
Caution: When the breaker is tripped off because
wait after 30min to turn on it again, otherwise may cause the breaker damage.
The battery string's system will check itself, if work normal the battery string system will go
to self-check mode.
If the BMS and all battery modules are working normally, every status LED will lighting
green, that's mean self-check are pass. Self-check will be finish within 10sec.
18PIHV0802
BMS (Battery Control Modules) of battery string:
st
over current or short circuit, must
14 / 27