3.5.1 Handling and placement of the battery module

Sigel battery module is 24kg. If without handling tools must have more than 1 manto handling
with it.

3.5.2 Handling and placement of the rack

If without handling tools must have more than 4 men to handling with it.

3.5.3 The fix and installation of the rack

The rack must be fixed installed on the basement or carriage on the wall with M10 screws.
Battery rack basement holes bitmap (unit: mm):
Battery
rack
mm):

3.5.4 Control Module (BMS) and all Battery Modules install into the Rack

Install the buckle nuts. The position of nuts must meet the position of the control module (BMS)
and all battery modules.
Install the control module (BMS) and all battery modules in. Each module uses 4 screws to fix.
Refer to chapter 3.5.1
18PIHV0802
wall
10 / 27
fixed holes bitmap (unit:

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Powercube-h2Powercube-x1

Table of Contents