Download Print this page

Insinger Commander 18-6 Technical Manual page 19

High temperature door type dishmachine

Advertisement

Tank Heat Temperature Adjustment
A temperature control board is provided in the control
panel for easy adjustment of tank temperature.
Though tank temperature is set during factory testing
it is sometimes necessary to re-adjust the temperature
at start-up.
1. Locate the temperature control board (P/N DE9-
251). Use the control panel layout drawing located
in PART 7, Electrical Schematics and Parts.
2. Adjust the tank temperature to the correct
temperature by turning the potentiometer located
on the temperature control board. An arrow on the
potentiometer indicates increase.
NOTE:
Correct temperatures are:
Wash - minimum 160
Final Rinse - 180
DE9-251: Tank Temperature Control Board
Commander 18-6 Technical Manual 2018
®
PART 5
F
O
F to 195
F
O
O
MAINTENANCE & REPAIR PROCEDURES
Troubleshooting Tank Temperatures
If the temperature does not change follow the below
procedures.
Electric Heat:
1. Check the temperature control board (P/N DE9-
251) for proper operation. If the temperature
control board is faulty, replace.
2. Verify tank heat contactor is working correctly. If
not, replace.
3. Verify all immersion heaters are working properly
and are not limed. If not, replace.
Steam Heat:
1. Check the temperature control board (P/N DE9-
251) for proper operation. If the temperature
control board is faulty, replace.
2. Verify steam pressure per machine specifications.
3. Verify steam trap is not clogged. If so, clean and/or
replace.
Immersion Heater Replacement (SK-4703)
1. The immersion heater MUST be completely
submerged at all times. If this is not the case
contact a qualified service technician. The heated
surface should never be in contact with sludge.
2. Remove the housing covering the wiring
terminations. Disconnect the immersion heater
wires.
3. Remove the immersion heater by loosening and
removing the large hex nut.
4. The taper side of the nut must face toward wall of
tank.
5. Remount Hi-Temp cutoff switch to top heavy
element. (See dwg. #1433-3).
NOTE:
Use plumbers putty as gasketing
around the immersion heater
installation nut.
www.insingermachine.com
17
800-344-4802

Advertisement

loading

This manual is also suitable for:

Commander 18-6cCommander 18-6hCommander 18-6hc