Installation
Figure 2-15:
2.8

Installation checklist

Review the following checklist prior to turning the power on to the transmitter after
installation has been completed:
20
Current source and sink drawing
Ensure that the transmitter and sensor are properly and firmly mounted.
Ensure that stopping plugs are securely tightened on any unused conduit entries.
Ensure that the transmitter and sensor are not obstructed, such that they are
accessible and the particulate matter is not inhibited from reaching the sensors
optical path.
Ensure adherence to applicable local guidelines and requirements on wiring and
sealing of equipment in hazardous and non-hazardous areas.
Ensure that proper shielding and grounding practices are adhered to and local codes
are being followed.
Check system operational voltage and conditions and ensure that they are within
the applicable specifications of the transmitter and sensor.
Verify wiring at all termination and junction points (transmitter, junction box, and
power supply).
Ensure that the transmitter housing cover and sensor cap are tightly secured.