Chapter 2
Installation setup
Installation procedure
Uponor recommends following the process described below
to guarantee the best possible installation results.
Step
Procedure
1
Installation preparation
2
Installing the base unit
3
Connecting the expansion module (optional)
4
Installing themostats
5
Finish installation
Climate Control Zoning System II installation and operation manual | Chapter 2 – Installation setup l 5
Installation preparation
Before starting the installation:
• Verify the contents of the package with the packing list.
• Check whether an external temperature sensor is
to be installed with a compatible thermostat.
• Study the wiring diagram in the end of this manual or
inside the base unit.
Figure 2-1: Base unit with wiring diagram
Placement
To determine where to best place the Climate Control
Zoning System II components, follow these guidelines:
• Ensure the base unit can be installed close to the manifold.
Note: Each manifold must have its own controller
(unless proximity of second manifold allows for it).
• Ensure the base unit is supplied by a 24 VAC,
50 VA transformer.
• Ensure all installed components are protected from
running or dripping water.
Need help?
Do you have a question about the Climate Control Zoning System II and is the answer not in the manual?
Questions and answers