Step 8: Complete Installation of Junction Box or an Enphase Q Aggregator

A. Connect the Enphase Q Cable into the Enphase Q Aggregator. The Enphase Q Cable uses
the following wiring color code. A ground lug is provided on the Q Aggregator for convenient
module/rack/balance of system (BOS) grounding.
B. Refer to the wiring diagrams on page 42 for more information. Wire colors are listed in the
following table.

Step 9: Connect the PV Modules

WARNING: Electrical shock hazard. The DC conductors of this photovoltaic system are
ungrounded and may be energized.
A. Connect the DC leads of each PV module to the DC input connectors of the corresponding
microinverter.
DC Connector
Status LED
B. Check the LED on the connector side of the microinverter. The LED flashes six times when
DC power is applied.
C. Mount the PV modules above the microinverters.
20
Wire Colors
L1 – Black
L2 – Red
AC Connector
© 2017 Enphase Energy Inc. All rights reserved.